We have a problem with the EPMContextMember in SAP BPC 10.1 (Netweaver version).
Actually we are using several workbooks at the same time.
A user is using 2 different workbooks. The two workbooks have a parameter called "Budget", which are referenced to the same dimension.
In workbook number 1 the user is preparing the "Budget" of the actual month 'SEP.2015', but sometimes the user has to verify a value of a particular project in the last month Budget... In that case the user opens another workbook (number 2) and change the parameter "Budget" to "AUG.2015". That action changes the value of the Budget parameter in the Context from SEP.2015 to AUG.2015.
When the user returns to the Workbook 1, the value of the parameter "Budget" automatically switches from "SEP.2015" which is the valid value to "AUG.2015"
Is there a way to avoid this behavior?. We need a solution to maintain the parameters with different values, not with the value in the Context.
Our EPM Version is:
10.0 SP 22 . NET4
Build: 9188