In our system, currently MRP doesn't do capacity check at planned order level.
Example; On Sept-30 we have requirement of 100,000 KG and planned order fixed lot size is 10,000 KG. Work center capacity is 10,000 KG per day. Than means per expectation MRP should place 1 planned order per day.
But in our system when MRP creates planned order for Sept-30, it place all 10 planned order on same date of sept-30. that means it does not check work center capacity, but when we convert those planned order to process order system does check capacity and place planned order per available capacity.
Can you please suggest, how to change system behavior so MRP check capacity at planed order level?
Reply appreciated.