Hi
I want to cost component data to CO-PA product wise with variance calculation please correct me if i am wrong
1) I had activate the settlement profile by giving the tick mark on " Variance to costing based PA" check box (OKO7)
2) same settlement profile assigned to the process order type (CORN)
3) Create the Value field for three activities 1) lab 2) mac 3) pow etc., as vv01, vv02 & vv03
4) Maintain the PA Structure (KEi1) assign all the value field along with source field for all the variances
5) do the settlement of the process order of variance through k088 where COPA document will generate
above setting is working fine but now client expiation increase they want all the cost component structure need to flow to COPA
so i maintained the
1) costing key (001) there with transfer std cost estimate - Radio button activated & Price indicator as mtrl cost est posting date
2) here i have confusion Assign costing key to material type = costing key through (KE4J) along with KEPC maintenance (what to maintain i am not sure) required expert advise
3) KE4R - i maintained as per the Costing component wise with value field after that what are the step i not confidence
need your further guidance
Thanks in advance
Thanks
Trinath